日处理3500吨某铅锌矿选矿厂设计.doc
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 处理 3500 吨某铅 锌矿 选矿厂 设计
- 资源描述:
-
1、日处理3500t某铅锌矿选矿厂设计摘要:按照毕业设计任务书的要求,进行了某铅锌矿优先浮选3500吨/日选矿厂设计,产品为铅精矿和锌精矿。在收集相关设计资料的基础上,确定了各车间的工作制度,对设计工艺流程进行了选择和论证,确定了设计的工艺流程,即:破碎采用三段一闭路流程,磨矿采用一段闭路流程,浮选采用优先浮工艺,精矿采用先浓缩后过滤的两段脱水。对设计工艺流程进行了工艺指标计算,包括破碎、筛分、磨矿、浮选(包括矿浆流程)和脱水流程。对破碎、筛分、磨矿、分级、浮选及脱水设备进行了选择计算,确定了工艺所需的工艺设备。进行了厂房总体布置,并进行了厂房内的设备配置。根据选厂房的地形条件,沿山坡地布置,其中
2、,粗碎、中细碎厂房分开布置,粗碎、中细碎厂房平行等高线配置。磨矿浮选共厂房配置,其中磨矿采用纵向配置,浮选机采用横向配置。浓缩机配置在露天,过滤机与精矿仓配置在厂房内。完成了粗碎、中细碎、筛分、磨浮车间平断面图、数质量及矿浆流程图和设备联系图。 关键词:选矿厂设计 铅锌矿 浮选 A lead-zincuflotation 3500 ton / day concentrator was designed Abstract:In accordance with the requirements of the graduation design task book, a lead-zincuflot
3、ation 3500 ton / day concentrator was designed, the products are lead concentrate and zinc concentrate. Based on the collection of relevant design information, the work of the workshop system,the selection and verification of the design process, the design process, namely:crushing three-stage closed
4、 circuit grinding period of closed circuitflotation using apriority floating craft, concentrate concentrated filter for both dehydration. In calculating the process of the design process, including crushing, screening, grinding, flotation (including pulp processes) and dehydration processes. Crushin
5、g, screening, grinding, classification, flotation and dewatering equipment selection, the process equipment required for the process. Plant general layout and configuration of equipment inside the plant. According to the theplant selection terrain conditions, arranged along the hillside, which coars
6、e crushing,crushing plant arranged separately, crushing, crushing plant parallel to contourconfiguration. Grinding and flotation common plant configuration in which grindinglongitudinal configuration, flotation machine horizontal configuration. The concentrator isconfigured in the open air, filter a
7、nd concentrate compartment configuration in the plant.Completed a crushing, crushing, screening, grinding and floating flat cross-sectional view, the number of quality and slurry flow charts and equipment in connection with Figure 8. Keywords: concentrator design, lead and zinc ores, flotation 目录1 绪