西沟四矿5.00Mta新井设计.doc
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 西沟四矿 5.00 Mta 设计
- 资源描述:
-
1、摘要西沟四矿拥有四层可采煤层,煤层和煤厚分别是2#(5)、3#(5)、8#(2.5)、15(2.5)。煤层南北倾向约为4100m,东西走向约为5100m,井田面积约为20.91km2。平均倾角为12度。工业储量为448.07Mt,设计储量为416.17Mt,可采储量为374.69Mt。本设计从矿井的开拓、开采、运输、通风、提升及工作面的采煤方法等各个环节进行了详细的叙述,设计严格遵守设计规范和煤矿安全规程,整个矿井采用了先进的皮带运输,提高了运输能力,为矿井的增产打下了良好的运输基础。采煤方法采用倾斜长壁综合机械化采煤方法。工作面支护方式为液压支架支护方式,端头支护采用端头支架。本设计采用立井
2、多水平开拓,主井采用箕斗提升,副井采用罐笼提升,大巷采用集中布置。通风方式为中央并列式。本次设计是西沟四矿新井设计,地质资料都是在实习矿上搜集的,在指导教师的指导下,并合理运用平时及课堂上积累的知识,查找有关资料和文献,力求设计出一个高产、高效、安全的现代化矿井。关键词:煤矿开采;开拓布置;运输;开采方式;通风AbstractWest Ditch four mine four coal seams, coal and coal thickness were 2# (5), 3# (5), 8(2.5)and 15# (2.5). Coal seam and tendency to approx
3、imately 4100m, the east-west direction is about 5100m, Idas area is about 20.91km2. Mean angle of 12 degrees. Industrial reserves of448.07tons, design reserves of416.17tons, recoverable reserves of 374.69tons. This design from the mine development, mining, transport, ventilation, and enhance the wor
4、king face coal mining method and other aspects were described in detail the design, strictly abide by the design code and coal mine safety regulations, the whole coal mine using advanced belt transportation, improve transport capacity, as the mine production laid good transport infrastructure. Incli
5、ned long wall mining method using comprehensive mechanized coal mining method. The face support for hydraulic support, end support the end bracket. The design of shaft using single level development, main shaft skip hoisting in auxiliary shaft adopts, the hoisting, lane use centralized layout. Venti
6、lation system for the central parallel. The design of Fushan four mine new design, geological data are collected in the practice of mine, under the guidance of teachers, and rational use of peacetime and class of accumulated knowledge, finding relevant data and literature, to design a high yield, hi
7、gh efficiency, safety and modernization mine.Key words: coal mining; development layout; transport; mining method; ventilation目录前言11矿区概况21.1矿区概述21.1.1矿区地理位置及行政隶属关系21.1.2矿区地形地貌21.1.3 矿区气候条件及地震情况31.1.4 水源供应情况31.1.5矿区内有关的主要企业单位31.2 井田及其附近的地质特征41.2.1 井田的地层层位关系41.2.2井田内的地质构造及变动41.2.3水文地质41.3 煤层质量及煤层特征51.