城郊煤矿2.4Mta新井设计【专题煤矿充填采矿法浅析】.doc
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 专题煤矿充填采矿法浅析 城郊 煤矿 2.4 Mta 设计 专题 充填 采矿 浅析
- 资源描述:
-
1、摘 要本设计包括三个部分:一般部分、专题部分和翻译部分。一般部分为城郊煤矿2.4Mt/a新井设计。城郊矿位于河南省永城市境内。井田南北走向平均长8km,东西平均宽6.5km,面积约45.1km2。 井田内可采煤层为二2煤,其赋存稳定,厚度平均为2.95 m,倾角平均8,为缓倾斜煤层。井田内工业储量为1.97亿t,可采储量为1.85亿t。矿井平均涌水量为376 m3/h,井田中各煤层沼气含量一般小于0.5cm3/g,属低沼气矿井。各煤层均无煤尘爆炸危险。各煤层均属不自燃发火煤层;地温2930。城郊煤矿年设计生产能力为240万t/a,服务年限为55.09年。采用立井开拓,立井直接延深的开拓方式。工
2、作制度为“四六”制,矿井年工作日为330天。第一水平标高为560m,第二水平标高为-740m。矿井采用倾斜长壁综合机械化采煤法,一次采全高。矿井布置一个综采工作面,面长240m。煤炭通过胶带输送机运输,采用矿车进行辅助运输。矿井初期通风方式为中央并列式。一般部分共包括10章:1、矿区概述与地质特征;2、井田境界和储量;3、矿井工作制度、设计生产能力及服务年限;4、井田开拓;5、准备方式带区巷道布置;6、采煤方法; 7、井下运输;8、矿井提升;9、矿井通风与安全;10、设计矿井基本技术经济指标。专题部分题目是煤矿充填采矿法浅析,主要是研究了煤矿充填法技术,对煤矿充填法做了全面的陈述。翻译部分主要
3、内容是关于对急倾斜煤层开采方法的探讨,英文题目为:Research of Steep Coal Seam Mining Methods based on Fuzzy Comprehensive Evaluation。关键词:立井;两水平;带区;中央并列式通风ABSTRACTThis design includes three parts: the general part, the special subject part and the translation part.The general part is a new design for Chengjiao mine.The Cheng
4、jiao Mine field lies in Yongcheng in Henan province. The boundary of the mine field runs 8km from north to south and 6.5km from west to east on average. The total plane area of the mine is about 45.1km2. There is only one exploring layer-number two. Its average thickness of the seam is 2.95m and its
5、 stable and flatly inclined. Its dip angle is 8 degree on average. The industry reserves of the mine field are 197.4 million tons and the useable reserves are 185.1 million tons. The average inflow rate in Chengjiao mine is 376m3/h. It is a lower gassy mine. The coal dust doesnt have explosion hazar
6、d as well as the self-combustion tendency.The productive capacity of Chengjiao Mine is 2.4 million tons per year,and the service life is 55.09 years. The work system is 4-shift with a 6-hour workday. It produces for 330 days a year.Therere two working levels in the mine. The first development level
7、is located at the -560m, and the second is at the level of -740m. The comprehensive mechanized longwall caving method along the dip is used in Chengjiao Mine.There is only one working face in the mine. It is comprehensive mechanized coal face. The length of the face is 240m, and the designed product
展开阅读全文