长治红兴煤业15号煤层开采设计.doc
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 长治 煤业 15 煤层 开采 设计
- 资源描述:
-
1、山西大同大学煤炭工程学院2016届本科生毕业设计摘 要最近几年来,煤炭行业的发展势头很好,越来越多的人力和金钱投入到了煤矿的生产和建设中。本设计就是在这样的的前提下对山西省长治市红兴煤业煤矿产值进行实地实习后,经过认真而详细的分析,计算后编写的。井田面积为2.18km2,批准开采515号煤层,批准矿井生产能力由为30万吨/a。井田内煤层赋存比较稳定,煤层平均倾斜角度为39,平均煤厚4.33m,地质条件比较简单,在井田范围中部有断层,矿井二氧化碳和瓦斯含量相对不高,涌水量也不大。根据实际的地质资料情况对矿井开拓方式、准备方式和采煤方法进行了初步设计,该矿井设计采用立井开拓方式,综合机械化采煤工艺
2、,倾斜长壁采煤法,大采高一次采全厚采煤法,使用全部跨落法处理采空区。矿井采用中央并列式通风,井底车场是刀把式环行车场,并对矿井提升、矿井运输、矿井通风和矿井排等各个生产系统进行设备选型计算。设计时需要根据现有经济技术条件,尽可能采用先进的开采技术和设备,以及对矿井安全技术措施和环境保护提出要求,完成整个矿井的初步设计。关键词:立井、大采高、走向长壁、采全厚ABSTRACT In recent years, the coal industry has been a good development, more and more money and manpower to the coal min
3、e construction and production. This is designed in such a premise of changzhi, Shanxi Province in,hongxin mine coal mine after on-the-spot investigation practice, after a careful and detailed analysis, written after calculation. Field area of 2.18 km2, approved mining 5 15 # coal seam, approval of t
4、he mine production capacity from 0.3 Mt/a. Within the field of coal seam occurrence is stable, the average Angle of coal seam is 39, and the average coal thickness 4.33 m, the overall geological condition is simple, in the central field range have faults development, carbon dioxide and,methe,content
5、 is relatively high, water inflow, it should not. According to the actual geological data of the main mode of mine development, preparation method and the coal mining method has carried on the preliminary design, one level of the mine design adopts the vertical development way, the level of comprehe
6、nsive mechanized coal mining technology, inclined longwall mining method, the large mining height are broken once mining thick coal mining method, using all fall across method and treatment of mined-out area. Mine with middletogether ventilation, bottom knife fantasy hoop yard, and the mine promote,
7、 mine,trasprote, mine,ventilation , and equipment selection of mine drainage, and other,pruduction systems. When the design according to the existing economic and technological conditions, as far as possible the use of advanced production technology and equipment, as well as to the mine safety techn