乌溪江水电站有压引水式地面厂房设计说明书(二).doc
- 配套讲稿:
如PPT文件的首页显示word图标,表示该PPT已包含配套word讲稿。双击word图标可打开word文档。
- 特殊限制:
部分文档作品中含有的国旗、国徽等图片,仅作为作品整体效果示例展示,禁止商用。设计者仅对作品中独创性部分享有著作权。
- 关 键 词:
- 江水 电站 引水 地面 厂房 设计 说明书
- 资源描述:
-
1、摘 要乌溪江水电站座落于浙江省乌溪江湖南镇,属于梯级开发电站,根据地形要求,其开发方式为有压引水式。坝区地质条件较好,主要建筑物(砼非溢流坝),泄水建筑物(砼溢流坝),引水建筑物(有压引水遂洞,调压室),地面厂房。水库设计洪水位238m(千年一遇),相应的下泄流量4800m3/s;校核洪水位240m(万年一遇),相应的下泄流量8500m3/s;正常挡水位232m.本设计确定坝址位于山前峦附近,非溢流坝坝顶高程242m。坝底高程112m。最大坝高130m。上游坝坡坡度1:0.1,下游坝坡坡度1:0.80,溢流坝堰顶高程224.54m。引水遂洞进口位于坝址上游凹口处,遂洞全长1290m。洞径8.6
2、m,调压室位于厂房上游260m左右处,高程255m的山峦上,型式为差动式(大、小井分离式)。厂房位于下游荻青位置。设计水头96m,装机容量45.6=22.4万Kw,主厂房净宽18m,总长77.5m。水轮机安装高程115.78m,发电机层高程125.5m,安装场层高程129m(比下游校核洪水位128 m略高)。厂房附近布置开关站,主变等。受地形限制,为了减少开挖量,尾水平台兼作公路用,坝址与厂区通过盘山公路连接,形成枢纽体系。由此可见,本设计是合理可行的。关键词:水利枢纽;挡水建筑物;泄水建筑物;稳定;应力;水轮机;选型;引水隧洞;调压室;厂房;发电引水隧洞。Abstract The Wuxij
3、iang hydropower station is located in HuNan Town in ZheJiang province ,which belongs to a chain of exploitation .According to the demand of topographic form ,I choose diversion hydropower station . The geology condition is good .The main construction conclude the water retaining structure (the concr
4、ete non over-fall dam) ,the release works (the concrete over fall dam) ,the diversion structure (pressure seepage tunnel ,the surge-chamber ) ,and the surface power station .The design water level is 238m ,its corresponding flow amount is 5400m3/s .The check level is 241.5m ,its corresponding flow i
5、s 9700 m3/s .The regular water retaining level is 232m .The dam site is near the former saddle .The crest elevation of the non-over-fall dam is 242.51m ,and the base elevation is 112m ,The max height of the dam is 130.51m ,The upstream dam slope is 1:0.2 ,the downstream dam slop is 1:0.7 ,the spillw
6、ay crest elevation is 226m .The inducer of the seepage tunnel is located at the recess place ,The length of tunnel is 1100m ,the diametric of which is 8.2m .The surge-chamber is located at the mountain , which is 260m from the work shop building and is type is differential motion.The workshop buildi
7、ng is located at downstream ,the design level of the turbine is 94.92m , the equipped capacitor is 17104Kw ,the clean width is 16m , its whole length is 72m . The fix level of the turbine is 115.45 m , and the height lf dynamo is 126.00m , the level of the adjustment bay is 129.70m (higher than the